Replacement of the Ruebisbach water pipeline, Kloten
Soil science construction supervision (BBB)
The project
Location: Kloten (ZH)
Customer: Industrielle Betriebe Kloten AG (ibk)
Phases: and commissioning
Duration: 2022-2023
A new replacement had to be built for the Ruebisbach transport water pipeline in Kloten. The pipeline ran over a length of around 500 m across open agricultural land, which was largely designated as a crop rotation area FFF. To cross the Rousbach stream and Weinbergstrasse, two sections of approx. 15 m and approx. 60 m length respectively were constructed using jacking pipes. A start and finish pit had to be created for each section.
The pipeline construction and the temporarily used areas for installation sites, construction slopes and start and finish pits affected large areas of ground. In order to ensure proper handling of the soil and correct recultivation, the responsible licensing authority therefore required the use of a soil science construction supervision (BBB).
Ecosens AG's BBB provided expert support for the project during the four-month construction phase and carried out various clarifications and surveys. Unexpectedly, the pipeline route also ran through a previously unknown former landfill site, which led to further challenges. Thanks to the excellent cooperation of all parties involved, the project was completed successfully and in an environmentally friendly manner.
Procurement and evaluation of existing data on chemical and physical properties of the soils concerned (soil maps) and verification by means of field surveys
Evaluation of soil protection measures and preparation of a specification for soil monitoring during construction
Participation in construction meetings, advice and expert support for the client, site management and the contractor during ground work
Soil science construction supervision during the entire construction and repair work, monitoring and implementation of measures for physical and chemical soil protection and recultivation
Success control regarding preservation / restoration of soil fertility by means of soil profiles with hand soundings
Challenges
Large areas of agricultural land and crop rotation areas affected as well as challenging access and construction site logistics with temporary construction roads
Undercrossing of a road and a stream by means of jacking pipes and construction of corresponding start and finish pits
Difficult seasonal weather conditions
Digestion of heavily contaminated excavated material from a previously unknown landfill site in the pipeline route, waste sampling and material classification, coordination with disposal company
Our solutions
Rapid project familiarization and very high flexibility for short-term clarifications and construction site assignments
Establishing personal contact with all stakeholders, close cooperation with all parties involved, including executing machine operators and site managers
Development of case- and situation-specific solutions and measures for soil protection, rapid and pragmatic implementation on the construction site
Rapid project familiarization and very high flexibility for short-term clarifications and construction site assignments
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.